[FNS-10] Scheduled tasks where the end date is before the start date

Description

The problem

If a scheduled task is given an end-date that pre-dates the start date, the task will bypass the end-date (ignoring it) and continue to run.
For example:

  • Start Date: 01-Aug-2011
  • End Date: 01-Feb-2011

How can I stop this from happening?

Please ensure the end-date comes after the start-date to avoid this issue.
For example:

  • Start Date: 01-Jan-2011
  • End Date: 01-Apr-2011

Issue Details

Type: Technote
Issue Number: FNS-10
Components: DailyStatus Report
Environment:
Resolution: Fixed
Added: 07/09/2011 13:19:37
Affects Version:
Fixed Version: 1.0.0
Server:
Platform:
Related Issues: None